Excavation, Sub-Base Installation, Membrane & Screed Layer
This section covers the full preparation process up to the point where grids are laid:
- excavation
- sub-base installation
- compaction
- membrane placement
- screed layer and levelling
If you follow this in order, you end up with a flat, stable surface that makes grid installation straightforward.
Step 1: Excavation – how deep to dig
Work backwards from the finished surface.
Typical excavation depth (guide only)
For a driveway on medium ground using 40 mm grids:
- Gravel infill + grids: ~40–50 mm
- Screed layer: ~20–30 mm
- Sub-base: ~150 mm
Total excavation is usually around 220–240 mm below finished level.
For lighter-duty bases (paths, shed base on good ground):
- Sub-base: 75–100 mm
- Total excavation often 150–180 mm
Always allow a bit of extra depth rather than trying to make it exact.
Step 2: Be aware of services
While excavating, actively look for:
- waste pipes
- water pipes
- electric or gas services
- drainage runs
Services can be much closer to the surface than expected, especially near buildings. If you uncover something:
- stop digging locally
- reassess your depth
- protect or bridge over it if needed
Never assume services are deeper. In most cases they will be but its always better to be safe than sorry.
Step 3: Manual vs machine excavation
I excavated both my drive and gravel grid base manually. So it can be done, but it’s very hard work.
For anything beyond a small area:
- a mini digger
- or mechanical assistance of some kind
will save huge amounts of time and energy.
Even a small machine turns days of digging into hours.
Step 4: Prepare the excavated ground level
Once excavated:
- remove loose material
- roughly level the ground
- remove any soft pockets
If the ground is soft, this is where a woven membrane goes in under the sub-base to provide reinforcement.
For a relatively firm surface, you can run the wacker plate over the ground to add some extra compaction prior to adding the sub base.
Step 5: Install the sub-base (Type 2)
For most DIY installs, MOT Type 2 is the best option.
Why:
- compacts reliably
- spreads load well
- forgiving for DIY work
- still drains sufficiently
Install in layers
- Lay in 75–100 mm layers
- Compact each layer fully before adding the next
Do not dump the full depth in one go.
Step 6: Compaction – take your time
Use a vibrating plate compactor (“whacker plate”).
Good practice:
- multiple passes
- different directions
- extra attention to edges
If the plate sinks or bounces:
- the layer is too thick
- or the ground below is too soft
Fix this before continuing.
Step 7: Lay the non-woven membrane
Once the sub-base is fully compacted and tidy:
- Lay a non-woven geotextile membrane over the entire surface
- Overlap joints as required
- Trim neatly at edges
This membrane:
- stops fines migrating upward
- allows water to drain through
This layer is essential and should not be skipped.
Step 8: Add the screed layer (this makes everything easier)
The screed layer sits on top of the membrane and directly under the grids.
- Typical thickness: 20–30 mm
- Material options:
- sharp sand (valid option)
- fine stone (2–6 mm, my preference)
The purpose of the screed layer is:
- levelling
- smoothing out small discrepancies
- giving the grids a flatbed to sit on
Levelling the screed layer (simple but effective)
I used a long straight edge and effectively “sawed” it across the surface.
This:
- flattened out small highs and lows in the sub-base
- made the surface far more uniform
- made grid installation much easier later
This step is well worth taking your time on.
Compaction of the screed layer (don’t overdo it)
I gave the screed layer a light pass with the whacker plate.
In reality:
- it doesn’t compact particularly well
- that’s normal
- its main job is levelling, not structural strength
A light initial pass to settle it is enough. Don’t try to over-compact it.
Where you should be at this point
Before moving on to grids:
- the sub-base should feel solid
- the membrane should be flat and intact
- the screed layer should be level and even
If it looks good now, the grids will sit properly.
Common mistakes to avoid
- Laying grids directly on the sub-base
- Skipping the non-woven membrane
- Trying to compact thick sub-base layers
- Overworking the screed layer
- Rushing this stage because “the grids will hide it”. They won’t.
The takeaway
This stage determines how easy the rest of the build will be.
If you:
- excavate properly
- compact the sub-base in layers
- lay the membrane correctly
- take time levelling the screed
Grid installation becomes straightforward instead of frustrating.